Project Overview
D.V.M. Utilities, Inc. completed tunnel boring operations for a stormwater improvement project at Detroit Metropolitan Airport in Romulus, Michigan. The installation required the construction of a 48-in steel casing using pipe jacking methods beneath active airport infrastructure.
Initially configured with a closed-face attachment for anticipated soft ground, the crew encountered stiff, cohesive clay conditions shortly after launch. By adapting equipment configuration in real time, the team maintained production and alignment while completing the installation under demanding subsurface conditions.