Project Overview
CH Nix Construction completed pilot tube assisted pipe ramming operations for Phase 1 of the 1800 North Sewer Realignment project in Salt Lake City, Utah. The project required multiple trenchless crossings beneath active rail lines and Interstate 15 as part of a broader utility relocation effort.
Using a staged installation approach, the crew installed pilot tubes to establish alignment before upsizing through intermediate diameters to final casing size. The method provided controlled accuracy while enabling efficient installation across multiple parallel drives in a highly constrained corridor.