Taxiway DS East–West Gates Tie-In Project

Project Name
Taxiway DS East–West Gates Tie-In Project
General Contractor
Iowa Trenchless – Panora, IA
Location
Denver International Airport, Denver, CO
Ground Conditions
Claystone with large boulders
Akkerman Equipment
WM480C-I Tunnel Boring Machine. 5000 Pump Unit and TBM accessories
Pipe
48-in ID Reinforced Concrete Pipe (59.5-in OD)
Total Length/Hard Rock Section
365 LF
Owner
Airport Authority

Project Overview

Iowa Trenchless completed conventional tunnel boring operations for the Taxiway DS East–West Gates Tie-In Project at Denver International Airport in Denver, Colorado. The project required installation of a storm sewer and deicing conveyance system beneath active taxiway infrastructure.

Operating in difficult ground conditions featuring claystone and large boulders, the crew advanced the tunnel to a deep receiving shaft while maintaining alignment accuracy. The installation supports critical airport infrastructure while minimizing disruption to ongoing operations.

Challenges

  • Excavating through claystone with large obstructions and boulders
  • Maintaining line and grade accuracy beneath active airport taxiways
  • Advancing to a deep receiving shaft under constrained site conditions
  • Ensuring uninterrupted airport operations during construction

Solution

  • Utilized the Akkerman WM480C-I TBM to manage excavation in mixed ground conditions
  • Deployed a 5000 Pump Unit to maintain consistent advancement and production
  • Applied controlled tunneling methods to maintain alignment accuracy through obstructions
  • Executed installation strategies to minimize surface disruption in an active airport environment

Outcome

  • Successfully completed the 365 LF tunnel installation beneath airport taxiways
  • Maintained accurate line and grade through claystone and boulder conditions
  • Achieved consistent excavation performance despite large obstructions
  • Minimized disruption to airport operations and surface activities
  • Enabled installation of critical storm sewer and deicing infrastructure