Project Overview
BTrenchless completed slurry microtunneling operations for the Boulder MSI Improvements project in Boulder, Colorado. The project required installation of a 60-in steel casing to house a 42-in wastewater pipeline conveying flows from Boulder Creek, while minimizing impacts to surrounding infrastructure and environmental features.
Microtunneling was selected to reduce surface disruption and avoid impacts to traffic and nearby private wells. Operating from a deep secant pile launch shaft, the crew executed two drives using slurry microtunneling methods to maintain control and alignment in mixed ground conditions.