Cottonwood & Hackberry Creek WW Interceptor Improvements

Project Name
Cottonwood & Hackberry Creek WW Interceptor Improvements
General Contractor
Super Excavators, Inc. - Menomonee Falls, WI
Location
Irving, TX
Ground Conditions
Clay
Akkerman Equipment
SL60C MTBM System, AZ-100 Guidance System, Lube & Jacking Can, ABIS, MT-K Jacking System
Pipe
60-in. Hobas™ FRP - Jacking Pipe
Total Length/Hard Rock Section
2,115-lf. curved (longest) / 4,670-lf (total project) - 7 drives

Project Overview

Super Excavators, Inc. optimized the microtunnel installation by replacing several shorter tunnel drives with the introduction of a 2,115-LF curved alignment. The curved alignment was continually monitored by the Akkerman AZ- 100 guidance system and the exceptional crews successfully completed the long drive on-target with low thrust requirements.

Challenges

  • Originally planned with multiple short drives, which would have increased setup time and project duration
  • Required maintaining line and grade over an extended curved alignment
  • Clay ground conditions demanded consistent performance to minimize downtime and jacking forces
  • Navigating a 2,115-LF drive—the longest of seven total drives—required precise control and monitoring

Solution

  • Super Excavators, Inc. optimized the plan by replacing several short drives with a single 2,115-LF curved alignment
  • Utilized the Akkerman SL60C MTBM System with the AZ-100 Guidance System to accurately navigate the curve
  • Integrated Lube & Jacking Can, ABIS, and MT-K Jacking System to maintain low thrust and high efficiency
  • The AZ-100 system provided continuous monitoring, enabling crews to stay on target throughout the long drive

Outcome

  • Successfully completed the 2,115-LF curved drive with precise accuracy
  • Crews maintained alignment and grade throughout all seven drives, totaling 4,670 LF
  • Low thrust requirements and efficient jacking reduced wear on equipment and minimized delays
  • Project demonstrated the value of combining experienced crews with advanced Akkerman guidance and microtunneling systems
  • The streamlined drive plan led to time and cost savings while maintaining high performance