Project Overview
Most likely the northernmost TBM pipejacking project performed in North America, TTC battled extreme weather and changing ground conditions along this 320-LF alignment. Anticipating permafrost along the entire run, the ground became soft after only 17-LF requiring TTC crews to change the TBM cutterhead to standard carbide tooling onsite to continue.